Roadmap: what is done, what is next, and every idea on the table
The route runs solid through what has shipped, stops at an open node on this week, and runs dashed through what is decided. Ideas that are not decided are listed on their own, with who raised them.
27 Sep 2026 · the order is decided · dates are the plan and move when the work does
shipped, datedin progress nowdecided, not startedidea, not decided
The project starts 8 Sep
Specification written 18 Sep
The first build runs in production 21 Sep
The first map, and a name 22 Sep
Sign-in and a second product 24 Sep
The crawl sends forms 25 Sep
The first test runs, proven 26 Sep
Decisions and a timeline 27 Sep
Week 0 · from 28 Sep
Week 1 · from 5 Oct
Week 2 · from 12 Oct
Weeks 3–4 · from 19 Oct
After the timeline · the MVP stage
Production stage
Later, researched
Ideas raised, not decided
13 so far · each becomes a planned item only after a decision, with its date
with a read-only demo link for clients and leads; half of it runs today
for friends and potential clients, once the value is visible; the public demo is dated weeks 3–4
votes, not a single model; a verify experiment is running
quick decisions in a corner instead of a screen
a conversation beside a canvas that draws what you are talking about
what the product does and what is switched on
code, docs, release notes and feedback, not only code
discovery, approval, then a post under Tim's name; nothing filed yet
steps with screens, who can, where it fails
the map as an MCP server
once real traces exist
after a phone crawl exists
one seat price with a credit limit and top-up is decided; no number yet
An idea of your own? Tell us in the demo form →